Transporter Payment Statements

eLOGIC / WEIGHBRIDGE / FINANCIAL-MONTH REPORT

Transporter Payment Statement

UNPRICED POPUP ENABLED · KG → METRIC TONS · R/TON · VAT

16–31 October 2024 · 2024-10-16 to 2024-10-31 · UJAO

Crysler: Connected Buick: Connected Transactions Audit Unpriced Audit Not Invoiced
Weight unit correction active. Raw Crysler and Buick API NETTWEIGHT is configured as kilograms and converted to metric tons (÷ 1,000) before calculating loads, statement tonnage and subcontractor payment. Previously displayed financial amounts were inflated because kilograms were treated as tons. Verify this configuration against an actual weighbridge slip before approving payments.
Show raw-weight-to-ton reconciliation (up to 5 loads)
WeighbridgeRECNOTRANNORaw NETTWEIGHT (kg)Converted (t)
Crysler 311590 822880 34,300.000 34.300
Crysler 311383 822673 34,860.000 34.860
Crysler 311359 822649 35,340.000 35.340
Crysler 311331 822621 34,280.000 34.280
Crysler 311305 822595 37,240.000 37.240
Statement Filters
Selected dates: 2024-10-16 through 2024-10-31 (inclusive)
Changes apply automatically. Both periods shows separate payment totals for each half of the month.
Completed Loads17
Vehicles Used1
Nett Tons (t)584.500
Selected dates2024-10-16 – 2024-10-31
Priced Loads0 / 17
Subcontractor Ex VATR 0.00
Subcontractor VATR 0.00
To Pay Incl VAT (partial)R 0.00
Saved Invoices / Already Invoiced Tickets Previously saved invoices and their exact ticket lists are always accessible, even without an API connection.
17 load(s) without pricing. Payable totals are partial until these loads are assigned.
Payment statement: 2024-10-16 through 2024-10-31 (inclusive)
eLOGIC / BLACKMAGIC
TRANSPORTER SUBCONTRACTOR PAYMENT STATEMENT

UJAO

Completed weighbridge loads for the selected payment period
STATEMENT TS-202410-P2-F7C29863 16–31 October 2024
Transporter / CompanyUJAO
Statement Period16 Oct 2024 – 31 Oct 2024
Date Generated29 Nov 2026
Reporting PeriodCompleted payment period
Vehicles1
Completed Loads17
Total Nett Tons584.500 t
Subcontractor Ex VATR 0.00
VAT on Completed LoadsR 0.00
Payable Incl VAT (partial)R 0.00
Transporter Summary 50 transporter groups this payment period
#TransporterCompleted LoadsVehicles UsedNett Tons (t)Priced LoadsTo Pay Incl VATStatement
1UJAO 17 1 584.500 0 / 17 R 0.00 partial
TOTAL (current selection)171584.5000 / 17R 0.00
Save Invoice · UJAOView Saved Invoices

0 already invoiced · 17 not yet invoiced · 17 still need pricing.

New uninvoiced tonnes
584.500 t
New invoice VAT
R 0.00
New invoice payable (partial until priced)
R 0.00

Save the remaining uninvoiced loads for 16–31 October 2024. Every saved invoice permanently captures the subcontractor, first/last transaction time, each ticket, its rate, VAT and totals. The normal statement still shows all transactions, including saved ones; only not-yet-invoiced loads are included in the new amount above.

Preview Current Statement
Automatic Train Pricing · UJAOVessels are manual
Set this once. When you open either payment period or the full month, new unpriced tickets carrying T9886, BT4534 or another explicit T/BT train reference automatically receive this saved train rate. Already-priced tickets keep their original saved rate. VS vessel tickets and unclear references always require manual pricing. All applied rates appear in the normal statement and Preview Invoice.
Vehicle Transactions, Pricing & Payments
1 registrations / groups · 17 completed loads
Tick the load checkboxes below to apply this rate only to those transactions (including previously priced loads). Apply to All covers this subcontractor's entire selected payment period, even other pages. Both options replace rates only for not-yet-invoiced tickets; saved invoice rates are locked. Select Unassign pricing to clear rates on uninvoiced loads.
0 loads selected on this page
Vehicle Registration Loads RECNO TRANNO Order No Source → Destination Material Nett Tons (t) Pricing / Rate (R per ton) Amount Incl VAT (R)
FLS801FS 17 completed loads Load 1 310753 822045 —
Other / manual
CS6 → NORTH MSS 33.340
Not assigned
Not priced
—
Load 2 310772 822062 —
Other / manual
CS7 → NORTH MSS 30.540
Not assigned
Not priced
—
Load 3 310801 822091 —
Other / manual
CS6 → NORTH MSS 33.220
Not assigned
Not priced
—
Load 4 310822 822112 —
Other / manual
CS6 → NORTH MSS 33.740
Not assigned
Not priced
—
Load 5 310853 822143 —
Other / manual
CS7 → NORTH MSS 31.580
Not assigned
Not priced
—
Load 6 310875 822165 —
Other / manual
CS6 → NORTH MSS 33.640
Not assigned
Not priced
—
Load 7 310898 822188 —
Other / manual
CS7 → NORTH MSS 34.420
Not assigned
Not priced
—
Load 8 310943 822233 —
Other / manual
CS6 → NORTH MSS 35.700
Not assigned
Not priced
—
Load 9 310966 822256 —
Other / manual
CS6 → NORTH MSS 37.100
Not assigned
Not priced
—
Load 10 311227 822517 —
Other / manual
CS6 → NORTH MSS 35.700
Not assigned
Not priced
—
Load 11 311251 822541 —
Other / manual
CS7 → NORTH MSS 32.340
Not assigned
Not priced
—
Load 12 311280 822570 —
Other / manual
CS6 → NORTH MSS 37.160
Not assigned
Not priced
—
Load 13 311305 822595 —
Other / manual
CS6 → NORTH MSS 37.240
Not assigned
Not priced
—
Load 14 311331 822621 —
Other / manual
CS2 → NORTH W4L40 34.280
Not assigned
Not priced
—
Load 15 311359 822649 —
Other / manual
CS2 → NORTH W4L40 35.340
Not assigned
Not priced
—
Load 16 311383 822673 —
Other / manual
CS2 → NORTH W4L40 34.860
Not assigned
Not priced
—
Load 17 311590 822880 —
Other / manual
CS2 → NORTH W4L40 34.300
Not assigned
Not priced
—
FLS801FS subtotal  ·  17 loads 584.500 0 / 17 priced R 0.00
GRAND TOTAL  ·  17 completed loads  ·  1 vehicles 584.500 t 0 priced / 17 unpriced R 0.00
eLOGIC · SUBCONTRACTOR PRICING

Assign Pricing to Unpriced Loads

UJAO · 16–31 October 2024

Unpriced loads17
Unpriced net tons584.500 t
Selected for pricing0 loads
Select Vehicle Registration RECNO TRANNO ORDERNO Source → Destination Nett Tons
FLS801FS 310753 822045 — CS6 → NORTH 33.340
FLS801FS 310772 822062 — CS7 → NORTH 30.540
FLS801FS 310801 822091 — CS6 → NORTH 33.220
FLS801FS 310822 822112 — CS6 → NORTH 33.740
FLS801FS 310853 822143 — CS7 → NORTH 31.580
FLS801FS 310875 822165 — CS6 → NORTH 33.640
FLS801FS 310898 822188 — CS7 → NORTH 34.420
FLS801FS 310943 822233 — CS6 → NORTH 35.700
FLS801FS 310966 822256 — CS6 → NORTH 37.100
FLS801FS 311227 822517 — CS6 → NORTH 35.700
FLS801FS 311251 822541 — CS7 → NORTH 32.340
FLS801FS 311280 822570 — CS6 → NORTH 37.160
FLS801FS 311305 822595 — CS6 → NORTH 37.240
FLS801FS 311331 822621 — CS2 → NORTH 34.280
FLS801FS 311359 822649 — CS2 → NORTH 35.340
FLS801FS 311383 822673 — CS2 → NORTH 34.860
FLS801FS 311590 822880 — CS2 → NORTH 34.300
Pricing is per metric ton. Each priced load uses the upstream raw NETTWEIGHT converted from kilograms to metric tons (÷ 1,000), then multiplies by its saved subcontractor-rate snapshot, with VAT calculated per line and rounded to cents. VAT-inclusive rates are NOT charged VAT twice. Monetary totals sum priced loads only; 17 unpriced load(s) are excluded, so the amount is partial. This is a subcontractor settlement statement, not a tax invoice.
Saved ticket corrections applied: 0.
Statement validation: 2 period-dated transaction(s) excluded because NETTWEIGHT is zero/negative or missing; 0 API row(s) excluded because TRANDATETIME could not be read; 0 exact duplicate(s) ignored; 1,710 completed load(s) have no TRANSPORTER; 0 completed load(s) have no TRUCKNO.
One completed load is one transaction whose TRANDATETIME falls within the selected date range (both periods, one half-month, or a custom range within the selected calendar month) and whose NETTWEIGHT is greater than zero. Unique vehicle count is based on TRUCKNO; missing numbers are not counted as vehicles. Crysler and Buick NETTWEIGHT values are configured as kilograms and divided by 1,000 to metric tons before any summary or R/ton payment calculations; verify against the weighbridge slip. Train rate defaults are configured per subcontractor; new unpriced T/BT train loads receive the selected tariff, while VS vessel loads need manual pricing. Saved pricing is a R/ton subcontractor rate snapshot; it does not overwrite API data. Money is calculated to two decimals per load, including VAT per saved price settings. The selected payment statement remains provisional until its payment period ends. When all transporters are selected, unique vehicles are counted across the whole fleet; the same truck can appear under more than one transporter. Upstream transaction data is never changed; local pricing assignments are saved in MySQL.